AnnouncedData centers

Digital Realty DFW45 data center

State filing: build Jun 2026 to Jan 2029

Garland

Approximate location

Digital Realty filed with the state for an 80 MW, 672,000-sq-ft data center (ten 8 MW suites) at 1602 Ferris Rd on its Garland campus, at an estimated cost of $300 million.

Why it mattersExpands Garland's existing data center cluster; brings tax base and large new power demand, plus multi-year construction.
Status
Announced
Expected
State filing: build Jun 2026 to Jan 2029
Category
Data centers
Last checked
Oct 19, 2026

Timeline

  1. Added to the Realust tracker as Announced.
  2. Digital Realty filed with the state for an 80 MW, 672,000-sq-ft data center (ten 8 MW suites) at 1602 Ferris Rd on its Garland campus, at an estimated cost of $300 million. Source
  3. Reported by DatacenterDynamics. Source

Source

DatacenterDynamics, September 15, 2026

We track publicly announced projects from official sources and local news and re-check them monthly. Plans and dates change; dates are targets, not promises. Map locations are approximate. Projects don't affect any city's Realust Score. See something out of date? Tell us.