Under constructionJobs & mixed-use

Core Scientific AI data center expansion

Completion est. 2027

Denton

Approximate location

Core Scientific is converting its Denton site into an AI supercomputing center in a $635M expansion, raising power use from 294 to 394 MW and its leased city land from 31 to 78 acres.

Why it mattersBig tax base boost; some residents worry about electric rates and grid strain.
Status
Under construction
Expected
Completion est. 2027
Category
Jobs & mixed-use
Last checked
Oct 19, 2026

Timeline

  1. Added to the Realust tracker as Under construction.
  2. Reported by Community Impact. Source

Source

Community Impact, May 7, 2026

We track publicly announced projects from official sources and local news and re-check them monthly. Plans and dates change; dates are targets, not promises. Map locations are approximate. Projects don't affect any city's Realust Score. See something out of date? Tell us.