Last updated Nov. 15, 2026. Each store below includes its project file: state construction filing, timeline, what’s planned on the site and what neighbors and officials have said.
North Texas is in the middle of a grocery-store building boom. H-E-B is pushing deeper into Dallas County, Kroger is opening its big Marketplace format along the growth corridors, and Costco, BJ’s, Trader Joe’s, Whole Foods and Sprouts are following the rooftops. Here is every new grocery store we’re tracking in Collin, Denton, Dallas and Rockwall counties: where it is, its status and when it’s expected to open, checked against city filings, state construction filings and the companies themselves.
BJ’s Wholesale Club in Mesquite opened Nov. 6. Next up: Kroger Marketplace in Anna opens Nov. 20 at 6 a.m., according to the City of Anna, and Kroger says its Sendera Ranch Marketplace should open before Thanksgiving. Bookmark this page. We update it as dates are announced.
Map: new grocery stores coming to North Texas
Numbers match the list below, in order of expected opening. Open rings are stores that opened since Nov. 2025. Tap a pin for details. Locations are approximate.
Opening next
Kroger Marketplace, Sendera Ranch
Tom Thumb, Lucas
Whole Foods, Frisco (The Mix)
Kroger Marketplace, Custer & Frontier
Kroger Marketplace, Fate
Trader Joe's, Preston & Spring Creek
Trader Joe's, Wylie (FM 544)
Sprouts, Anna (US 75 & Rosamond)
Costco, FM 544
H-E-B, W. University Dr.
H-E-B, Josey & Parker
Kroger Marketplace, Princeton
H-E-B, Firewheel Pkwy. & PGBT
H-E-B, Hillcrest & LBJ
Joe V's Smart Shop, Garland
H-E-B, FM 2499 & Waketon (proposed)
Timing is the company’s estimate where one exists; otherwise it comes from state construction filings or city approvals, which often slip. “No date yet” projects are approved or proposed but have no announced timeline.
Every new grocery store, in order
Kroger is finishing a 123,153-square-foot Marketplace store and fuel center at Sendera Ranch Boulevard and Rancho Canyon Way, inside Fort Worth city limits with a Haslet address. A Kroger representative told the city in July 2026 that the store should open before Thanksgiving. Kroger has not announced a firm date.

Under construction since fall 2025. A Kroger representative told Fort Worth's Board of Adjustment on July 15, 2026 that the store should open before Thanksgiving; the state filing projected completion by Oct. 5, 2026. Kroger hasn't announced a firm date or a hiring event.
- Dec. 16, 2024Kroger announces two new DFW Marketplace stores, including Sendera Ranch (date given by Community Impact)
- Jan. 27, 2025Kroger corporate affairs confirms the site is at the NE corner of Sendera Ranch Pkwy and Rancho Canyon Way; groundbreaking expected in 2025
- May 5, 2025State filing TABS2025018178 registered (123,153 sq ft, $10M)
- Sept. 2, 2025Reported under construction with a 2026 opening, part of Kroger's $160M four-store DFW push (about $40M per store; 1,200 jobs across the four)
- Oct. 6, 2025State filing estimated construction start
- Dec. 8, 2025CultureMap: Sendera Ranch, Anna and Little Elm under construction, expected to open in 2026 or early 2027
- July 21, 2026Fort Worth Report: store expected to open by Thanksgiving
- Oct. 5, 2026State filing estimated completion date (passed; no opening announced)
“As North Texas continues to grow, so will Kroger to meet the needs of the community”Keith Shoemaker, then-president, Kroger Dallas Division
Sources: TDLR, communityimpact.com, therealdeal.com, dallas.culturemap.com, fortworthreport.org
Tom Thumb is building Lucas's first standalone supermarket, a store of about 59,650 square feet at Parker Road and Southview Drive, with a Tom Thumb Express fuel center next door. The company says it opens later in 2026, and state filings target Dec. 1 for completion. No opening day has been announced.

Under construction. Grocery Dive (Mar 10, 2026, citing an Albertsons/Tom Thumb press release) said construction had started on the Lucas storefront and it is expected to open later in 2026. TDLR store filing targets Dec. 1, 2026 completion; fuel center filing targeted Sept. 20, 2026. No opening date, grand opening or hiring event found as of Nov 3, 2026.
- April 3, 2025Malouf Interests buys 42 undeveloped acres at Parker Rd & Southview Dr from JCBR Holdings (Younger Partners brokered; $6.42M Veritex loan) for a 130,000-sq-ft grocery-anchored center, 25,000-sq-ft restaurant village, 15 pad sites and a park; Tom Thumb identified as grocer via city public records
- April 3, 2025CultureMap reports Tom Thumb (per city of Lucas public records) at NW corner of Parker Rd and Southview Dr (FM 1378); construction expected Q4 2025, completion 2026
- July 16, 2025State filing of 59,655-sq-ft Tom Thumb store (TABS2025023696), $5.8M
- Oct. 27, 2025State filing of Tom Thumb fuel center 4807FC (TABS2026004319), $1.3M
- March 10, 2026Tom Thumb says construction has started on Lucas store; opening expected later in 2026
- Dec. 1, 2026State filing scheduled completion for store (scheduled, not confirmed)
“This will be our first true grocery store serving the community.”Lucas Mayor Dusty Kuykendall
Sources: TDLR, TDLR 2, therealdeal.com, dallas.culturemap.com, grocerydive.com, localprofile.com
H-E-B is building Denton's first store, a 133,975-square-foot grocery with a fuel station and car wash at the northwest corner of I-35W and Robson Ranch Road, inside Hillwood's Landmark development. In September 2026 H-E-B moved its target up to late 2026 or early 2027, and hiring began in August. No grand-opening date has been announced.

Under construction and hiring. H-E-B began hiring in August 2026, and in September it said it now expects to open before 2027, ahead of the early-2027 target it gave in April. The state filing's estimated completion for the store (June 10, 2026) has passed; the fuel station and car wash filing runs to Nov. 5, 2026.
- March 12, 2025State filing TABS2025013956 filed for 133,975-sq-ft store ($60.5M)
- March 13, 2025H-E-B announces first Denton store at NW corner of I-35W and Robson Ranch Rd in Hillwood's Landmark; land purchase not yet final; construction expected to start spring 2025
- July 2025H-E-B confirms Robson Ranch land purchase finalized (reported alongside announcement of second Denton store)
- March 20, 2026State filing TABS2026015544 for fuel station (8 pumps) and automatic car wash, $1.4M
- April 14, 2026H-E-B tells Community Impact the store will open early 2027
- Sept. 1, 2026H-E-B says it now expects to open before 2027 (Cross Timbers Gazette)
“This is a rapidly growing area, and we are excited to introduce this new H-E-B store to Denton and surrounding towns.”Mabrie Jackson, managing director of public affairs, H-E-B and Central Market
Sources: TDLR, TDLR 2, newsroom.heb.com, keranews.org, communityimpact.com, flowermoundnews.org
Kroger's 123,000-sq-ft Marketplace at the southeast corner of US 75 and Rosamond Pkwy. opens at 6 a.m. on Nov. 20, 2026, according to the City of Anna's Nov. 5 announcement. Across Rosamond, Rosamond Town Center (Academy, Hobby Lobby, Aldi, T.J. Maxx, Burlington, HomeGoods, PetSmart, EOS Fitness) broke ground in June 2026, with most buildings due in 2027.
Opening soon. The City of Anna said on Nov. 5 that the store opens at 6 a.m. on Nov. 20, 2026 (reported by Chron on Nov. 15). The TDLR store filing projected completion by July 22, 2026, and the fuel center filing projected Nov 6, 2026. Community Impact (Oct 2025) listed Anna among stores 'slated to open in 2026'. CultureMap (Feb 2026) said 2026 or early 2027.
- Sept. 2, 2025Kroger's $160M four-store DFW push names Anna (Rosamond Pkwy and US 75); construction slated to start in fall 2025
- Sept. 23, 2025State filing TABS2026001633 registered (2661 Rosamond Pkwy)
- Oct. 1, 2025State filing TABS2026002271 registered (123,000 sq ft, $18.2M)
- Oct. 23, 2025Community Impact lists Anna among DFW Marketplace stores slated to open in 2026
- Jan. 7, 2026State filing estimated store construction start
- Feb. 24, 2026CultureMap: Anna under construction, opening expected in 2026 or early 2027
- July 22, 2026State filing estimated store completion date (passed)
- Nov. 6, 2026State filing estimated fuel center completion (scheduled)
- Nov. 20, 2026Kroger opens at 6 a.m., per the City of Anna's Nov. 5 announcement
“Kroger is working hard to keep pace with North Texas' explosive population growth”Rudy DiPietro, president, Kroger Dallas Division (Dec 2025 statement)
Sources: TDLR, TDLR 2, therealdeal.com, communityimpact.com, dallas.culturemap.com, dallas.culturemap.com 2, chron.com
Frisco's first Whole Foods Market is being built at The Mix, 5302 Dallas Pkwy. at Lebanon Rd. A $7.5M interior build-out registered with the state runs from July 2026 to Feb. 2027. Whole Foods hasn't announced an opening date.
Store announced and reported 'under construction' at The Mix (formerly Wade Park) in July 2025; interior tenant finish filed with TDLR April 2026, running July 2026 to Feb. 2027. No opening date announced in sources read.
- Jan. 2025The Mix phase one breaks ground (per Local Profile)
- July 24, 2025Community Impact reports Whole Foods under construction at The Mix
- April 15, 2026State filing TABS2026017761: $7.5M, 40,190-sf tenant finish
- July 2026State filing estimated interior build-out start
- Feb. 2027State filing estimated completion (scheduled)
“Frisco residents will finally get the Whole Foods Market they have long wanted, thanks to the efforts of The Mix”John Keating, Frisco City Council member
Sources: TDLR, localprofile.com, communityimpact.com
A Kroger Marketplace broke ground in late Feb 2026 at the southeast corner of Custer Rd. and Frontier Pkwy. and is slated to open in early 2027.

Under construction. Ceremonial groundbreaking Feb 27, 2026. Kroger says early 2027; Community Impact (Oct 2025) reported March 2027. TDLR store filing projects completion June 18, 2027; fuel center Jan 25, 2027.
- About 34 acres commercial (grocery-anchored), nearly 11 acres multifamily (preliminary plan: 3 to 4 stories, about 300 units), about 79 acres single-family with a 300-home cap. Owner: Haggard Rhea Mills LLC. Grocer not named at the time. Article includes no site plan graphics.
- Feb. 11, 2025McKinney P&Z votes unanimously to recommend the 127-acre rezoning (staff recommended approval)
- March 2025McKinney City Council approves the rezoning (vote tally not reported)
- Oct. 23, 2025Kroger Marketplace named as anchor of Weitzman's Custer Frontier Marketplace (about 45,000 sq ft of shops and six pads); March 2027 opening reported
- Dec. 8, 2025Kroger announces McKinney as one of three Marketplace stores to break ground in 2026
- Feb. 27, 2026Ceremonial groundbreaking; Kroger says opening in early 2027
- April 10, 2026State filing TABS2026017349 registered
- April 17, 2026State filing TABS2026017935 registered (122,917 sq ft, $12.15M)
- June 18, 2027State filing estimated store completion (scheduled)
- At the Feb 11, 2025 P&Z hearing, four adjacent residents spoke against the rezoning, mainly the multifamily component. They cited density and fit with single-family character, strain on infrastructure, schools and emergency services, and traffic congestion. P&Z still voted unanimously to recommend approval.
“Retail is driven by rooftops, and the rooftops are coming.”David Palmer, Weitzman (developer), at McKinney P&Z, Feb 11, 2025
Sources: TDLR, TDLR 2, communityimpact.com, communityimpact.com 2, dallas.culturemap.com, dallas.culturemap.com 2
Kroger held a groundbreaking in March 2026 for a Marketplace store at William E. Crawford Ave. and the I-30 frontage road in Fate. Kroger says it opens in 2027. A state construction filing lists 735 S. William E. Crawford Ave. and a May 2027 completion.
Under construction. Ceremonial groundbreaking March 27, 2026. Kroger says the store opens in 2027. TDLR projects completion May 27, 2027. The city's Project Cactus timeline targets grocery and department store openings by the end of 2027 (this anchor is most likely Kroger, inferred).
- 267 acres at NW corner of I-30 and FM 551 (Memorial Pkwy), built in phases over 15 to 20 years: business district, mixed-use core along the Woodcreek Blvd extension, single-family homes, about 50 acres of greenspace. Project Cactus covers about 80 acres between Woodcreek Blvd and FM 551 with about 400,000 sq ft of retail, a 'Fortune 100' grocery and a department store (each at least 100,000 sq ft). The page does not link the site plan PDF.
- Nov. 2023Lafayette Crossing Planned Development application submitted. Traffic Impact Analysis followed in Dec 2023; staff recommended 'Approval with Conditions'.
- Dec. 4, 2025Gulf Coast Commercial Group and Nexus Real Estate Co. announce purchase of a 70-acre site for a Kroger-anchored center in Lafayette Crossing
- Dec. 6, 2025City of Fate announces Kroger Marketplace as first anchor of Lafayette Crossing (over 100,000 sq ft)
- March 27, 2026Ceremonial groundbreaking; Kroger says opening in 2027
- June 2, 2026State filing TABS2026021740 registered (100,099 sq ft, $13M)
- Aug. 3, 2026State filing estimated construction start
- May 27, 2027State filing estimated completion (scheduled)
- Public money: the city's Project Cactus agreement for the roughly 80-acre retail core reimburses up to $15M in infrastructure. Funding comes from about $9M in impact fees, $1M utility capital funds, $1.7M economic development sales tax and $3.3M general funds. It also includes a 10-year (2028 to 2037) performance agreement sharing 50% of the project's sales tax. The city projects more than $140M in new property value and about $2.8M a year in sales tax. The page does not name Kroger or give an approval date or vote. No documented opposition found.
Sources: TDLR, fatetx.gov, businesswire.com, dallas.culturemap.com
Trader Joe's filed plans for a store at 5900 Preston Rd. at Spring Creek Pkwy. in Plano. State construction filings show a December 2026 start and completion by June 2027; the company confirmed the plans but says no timeline is set, and the address could change.
Interior build-out filing only; Trader Joe's spokesperson Nakia Rohde confirmed plans but no timeline defined. Site is at Spring Creek Pkwy., across from the H-E-B that opened in 2022; would be Plano's second Trader Joe's (first at 2400 Preston Rd., opened Sept. 2012).
- Sept. 11, 2026State filing TABS2027000810, $900K, 12,526 sf interior build-out
- Sept. 15, 2026CultureMap reports filing; Trader Joe's confirms plans, no timeline
- Dec. 2026State filing estimated construction start (scheduled)
- June 2027State filing estimated completion (scheduled)
Sources: TDLR, dallas.culturemap.com
Trader Joe's filed plans for a store on FM 544 in Wylie. State filings show construction from March 2027 to June 2027; the company says no timeline is set, and the address could change.
Interior build-out filing; company confirmed plans, no timeline. CultureMap places it one block west of Wylie High School and a Kroger Marketplace.
- Aug. 17, 2026State filing TABS2026028052, $900K, 12,476 sf interior build-out
- Sept. 15, 2026CultureMap reports filing; Trader Joe's confirms plans, no timeline
- March 2027State filing estimated construction start (scheduled)
- June 2027State filing estimated completion (scheduled)
Sources: TDLR, dallas.culturemap.com
Sprouts Farmers Market is building a 23,299-sq-ft store at the northeast corner of Preston Rd. and Frontier Pkwy. in Celina, anchoring GBT Realty's 56,000-sq-ft Preston Crossroads. State filings list Feb. 2027 completion; the developer targets summer 2027.
TDLR accessibility plan review for the Sprouts store recorded complete Mar 30, 2026 (zabalist mirror of TDLR), with scheduled construction Mar 15, 2026 to Feb 15, 2027. GBT Realty (via REBusiness, Nov 10, 2025) planned a January start and summer 2027 completion for the 56,000-sq-ft Preston Crossroads. No independent confirmation of vertical construction or a permit found.
- July 15, 2025State filing of 23,299-sq-ft, $4.7M Sprouts store (TABS2025023514)
- July 16, 2025Community Impact reports Sprouts coming to NE corner of Frontier Pkwy and Preston Rd, opening 2027; mayor's social post cites 75-100 jobs
- Aug. 26, 2025State filing registrations for two GBT retail shell buildings (6,760 and 9,600 sq ft)
- Nov. 10, 2025GBT Realty announces 56,000-sq-ft Preston Crossroads anchored by a 23,262-sq-ft Sprouts plus ~33,000 sq ft inline retail in three buildings; construction to start January, complete summer 2027
- March 30, 2026State filing review complete for Sprouts store filing (per zabalist mirror)
- Feb. 15, 2027State filing scheduled completion (scheduled, not confirmed)
“Sprouts will be a wonderful addition to the community”Celina Mayor Ryan Tubbs (social media post, via Community Impact)
Sources: TDLR, zabalist.com, TDLR 2, communityimpact.com, rebusinessonline.com, zabalist.com 2
The City of Anna announced a Sprouts Farmers Market in June 2026 at the northwest corner of Rosamond Pkwy. and US 75, projected to open in summer 2027. A $4.9M state construction filing schedules work from Dec. 2026 to Sept. 2027.
Announced by the City of Anna (release dated June 12, published June 14, 2026): a 20,000+ sq ft Sprouts at the northwest corner of Rosamond Pkwy and US 75, construction expected to start summer 2026 and grand opening projected summer 2027, anchoring a center with restaurants, retail, medical, a convenience store and banking. TDLR plan review recorded complete Aug 6, 2026; TDLR scheduled start is Dec 7, 2026. No construction start confirmed.
- June 5, 2026State filing of 23,256-sq-ft, $4.94M Sprouts store #0727 (TABS2026022204) and 9,600-sq-ft retail shell (TABS2026022206)
- June 12, 2026City of Anna announces Sprouts at NW corner of Rosamond Pkwy & US 75 with GBT Realty; construction summer 2026, opening summer 2027
- Aug. 6, 2026State filing review complete for Sprouts filing (per zabalist mirror)
- Dec. 7, 2026State filing scheduled construction start (scheduled, not confirmed)
- Sept. 24, 2027State filing scheduled completion (scheduled, not confirmed)
“We are thrilled to introduce this vibrant, growing community to Sprouts' signature shopping experience”Tim Mondello, VP of Development, GBT Realty (City of Anna release)
Sources: TDLR, zabalist.com, ntxe-news.com, zabalist.com 2
Costco plans a ~165,000 sq ft warehouse with members-only gas and tire service on about 25.5 acres at 2002 W. FM 544. Wylie City Council approved the zoning in September 2026; state filings schedule construction from Oct. 2026 to Aug. 2027. No opening date announced.
Approved. Wylie's Planning and Zoning Commission unanimously recommended the zoning Aug. 18, 2026, and the City Council approved it in September. State filings describe a steel-frame warehouse of about 165,000 sq ft. Costco hasn't announced an opening date.
- About 25.5 acres; wholesale retail store, minor automobile repair (tires and batteries), member-only fueling station. Article (web excerpt) gives no square footage, pump count, parking or access details; the underlying city agenda packet was not located.
- Aug. 18, 2026Wylie Planning & Zoning Commission votes unanimously to recommend zoning change to Commercial Corridor with SUP (wholesale store, tire/battery service, member-only fuel)
Sources: murphymonitor.com
H-E-B plans a 126,841-sq-ft store at 2210 W. University Drive (US 380), with an estimated construction cost of about $30 million.
H-E-B told Community Impact in April 2026 the store is scheduled to open in fall 2027. TDLR filing lists a June 15, 2026 start; no source read confirms construction actually began.
- 2015H-E-B buys the land at University Dr. and Bonnie Brae St.
- July 2025H-E-B confirms second Denton store ('Denton #2', ~119,000 sq ft at the time) at NE corner of University Dr. and Bonnie Brae St., beside Rayzor Ranch Marketplace; begins city permit process
- Oct. 13, 2025State filing TABS2026003197: 126,841 sq ft, $30.25M, construction June 15, 2026 to Aug. 31, 2027
- April 14, 2026H-E-B tells Community Impact the store will open fall 2027
“This is a significant investment in our economy”Denton Mayor Gerard Hudspeth
Sources: TDLR, keranews.org, communityimpact.com
H-E-B plans a 121,228-sq-ft store at 1919 Parker Rd. (NE corner of Josey Ln. and Parker Rd.) with a gas station, car wash, drive-thru pharmacy and drive-thru restaurant. Carrollton approved zoning in Jan. 2026; state filings list $24M in construction from Aug. 2026 to Nov. 2027. No opening date announced.
Zoning approved unanimously Jan. 6, 2026. TDLR filings (May 7, 2026) schedule construction Aug. 10, 2026 to Nov. 3, 2027. No source read confirms groundbreaking or an opening date.
- ~120,000-sq-ft store, gas station, car wash, drive-thru pharmacy, drive-thru True Texas BBQ, covered grocery pickup, 600+ parking spaces; traffic impact analysis approved; three turn bays (two on Parker, one on Josey) and a new traffic signal at the main Parker Rd. entrance
- Nov. 24, 2025Planning & Zoning Commission public hearing, recommends approval (CultureMap date; Dallas Observer says Dec. 4)
- Jan. 6, 2026City Council unanimously approves zoning change for 17.2-acre tract
- May 7, 2026State filing registrations for store ($22.8M) and fuel station/car wash ($1.2M)
“We're excited to welcome H-E-B to Carrollton, the community that families and businesses want to call home.”Carrollton Mayor Steve Babick
Sources: TDLR, TDLR 2, dallasobserver.com, dallas.culturemap.com, communityimpact.com
Nearly 100,000-sq-ft Kroger Marketplace with pharmacy and a 14-position fuel center at Beauchamp Blvd and US 380, in the 66-acre Princeton Town Center. About 200 jobs.
Ceremonial groundbreaking July 15, 2026; the city said construction is underway (July 22, 2026). Kroger says late 2027. The TDLR filing (registered Sept 24, 2026) shows an estimated building start of Jan 28, 2027 and completion Oct 8, 2027, which suggests sitework now and vertical construction from early 2027 (inferred).
- PD 43 amendments to land use, parking, height and area rules, landscaping, signs, exterior wall construction standards and outdoor sales standards for the 66-acre center at N. Beauchamp Blvd and Princeton Dr (US 380). Tenants named: Kroger Marketplace, Home Depot, PetSmart, T.J. Maxx, HomeGoods, Hobby Lobby. This was the first time Kroger appeared in city filings. Vote outcome not reported in the source.
- Oct. 27, 2025City Council public hearing on PD 43 amendment for Princeton Town Center; first time Kroger named in city filings
- July 15, 2026Ceremonial groundbreaking; Kroger spokesperson says late 2027 opening
- July 22, 2026City confirms nearly 100,000 sq ft store, 14 fuel positions, about 200 jobs, nearly $40M Kroger investment; developer The Seitz Group
- Sept. 24, 2026State filing TABS2027001835 registered (99,992 sq ft, $10.7M)
- Jan. 28, 2027State filing estimated construction start (scheduled)
- Oct. 8, 2027State filing estimated completion (scheduled)
“This groundbreaking represents another exciting chapter in Princeton's growth story”Princeton Mayor Eugene Escobar Jr.
Sources: TDLR, princetonherald.com, dallas.culturemap.com, princetontx.gov
H-E-B is planning a 139,271-square-foot store, plus a fuel station and car wash, on about 25 acres along I-30 near FM 2642 in Royse City. State filings schedule construction from Jan. 4, 2027 to Jan. 28, 2028. H-E-B has not announced an opening date. It has said only that it is aiming for 2028.
H-E-B said site grading and infrastructure work would start fall 2026, with major construction 'shortly after the first of the year' (Jan. 4, 2027) and completion Jan. 28, 2028 per state filings. Store address per Herald Banner: 5048 I-30.
- Jan. 2026Royse City CDC secures performance agreements and infrastructure commitments with H-E-B (early 2026; terms not disclosed)
- May 14, 2026Royse City CDC announces H-E-B is officially coming to I-30 and FM 2642 as anchor of Royse City Town Center
- Aug. 3, 2026State filing for fuel station (8 pumps) and car wash, $1.9M
- Aug. 5, 2026Herald Banner reports ~$40M project, 140,000 sq ft, construction Jan. 4 (2027) to Jan. 28, 2028, site work fall 2026
“H-E-B is excited to begin construction on our Royse City location shortly after the first of the year”Mabrie Jackson, H-E-B managing director of public affairs (via Houston Chronicle)
Sources: TDLR, roysecitycdc.org, roysecityheraldbanner.com
H-E-B plans a 115,000-sq-ft store on 21 acres between Crist Rd. and Firewheel Pkwy. on the Bush Turnpike, next to Firewheel Town Center. Garland approved a development agreement with a $2.5M grant and tax rebates on May 19, 2026; permit records point to a spring 2027 start.
Council approved the agreement in May 2026; site still an undeveloped field as of mid-2026. What Now Dallas (Oct. 23, 2026) says construction is expected to begin next spring (2027) and permitting records list a March 2028 completion.
- Incentive terms only: 50% rebate for 10 years on real property, business personal property and sales tax; up to $1.2M development fee rebate; $2.5M cash grant; H-E-B to invest at least $17M; certificate of occupancy required by Dec. 31, 2030
- Feb. 24, 2026H-E-B announces plan for a store on 21 acres between Crist Rd. and Firewheel Pkwy. off PGBT; purchase not yet final
- May 19, 2026Council considers development agreement ($2.5M grant, 50%/10-yr tax rebates, up to $1.2M fee rebate); approved in May per Dallas Observer
- Oct. 23, 2026Permitting records point to spring 2027 start and March 2028 completion
“I believe this is great deal for the city.”Garland Mayor Dylan Hedrick (work session notes)
Sources: dylanhedrick.substack.com, newsroom.heb.com, dallasobserver.com, whatnow.com
H-E-B's first Dallas store: a 131,000-sq-ft H-E-B with a three-level parking garage on 10 acres at the southeast corner of LBJ Freeway and Hillcrest Road. Council approved rezoning Dec. 10, 2025. A state filing targets a March 2027 start and September 2028 completion.
Rezoning approved 14-1 in Dec. 2025. TDLR registration filed May 27, 2026 (owner C&H Acquisitions, LLC) with $52M cost and a March 1, 2027 to Sept. 6, 2028 schedule. H-E-B says opening likely 2028.
- ~127,000-sq-ft store on 10 acres with structured parking; H-E-B agreed to build a right-turn lane on Hillcrest Rd. and accepted deed restrictions
- Jan. 2025H-E-B's first Dallas location at LBJ and Hillcrest reported
- Dec. 10, 2025City Council approves zoning change 14-1
- May 27, 2026State filing TABS2026021349: $52M, store plus three-level garage, construction March 2027 to Sept. 2028
- Residents raised traffic congestion as the primary concern, plus noise and crime; some contrasted the number of north Dallas grocers with southern Dallas food deserts. Neighbors remained divided; council vote was 14-1.
- City Plan Commissioner Jack Kocks argued the plan does not conform to the ForwardDallas land-use plan.
“We are committed to serving Texans and look forward to bringing our first H-E-B store to the city of Dallas.”H-E-B statement
Sources: TDLR, dallasobserver.com, candysdirt.com, nbcdfw.com
Frisco's first Trader Joe's (12,500 sq ft) and up to 158 senior apartments on 9.4 acres at the southwest corner of Main St. and Majestic Gardens Dr. Planning and Zoning approved it unanimously in July; the council tabled it in August over traffic near a Frisco ISD campus, then approved it 6-0 on Oct. 6, 2026. No construction or opening date yet.
Zoning approved by council Oct. 6, 2026. No construction timeline, contractor, or TDLR filing found.
- Unanimous P&Z approval. Developer added resident/visitor parking, improvements along Majestic Gardens for traffic flow from nearby Frisco ISD campus, landscaping/streetscape and architectural revisions. No space counts or heights given.
- 9.4 acres total: 3.22 acres Trader Joe's, 6.18 acres senior living. Built in a single phase; senior living cannot open until Trader Joe's opens. Landowner SNS Frisco West Main Station LLC.
- Oct. 30, 2025Trader Joe's confirms it is considering a Frisco location
- July 28, 2026Frisco P&Z unanimously approves zoning change
- Aug. 2026City Council tables the project for more discussion (reported Aug. 19, 2026)
- Oct. 6, 2026City Council approves the mixed-use zoning
- Traffic, especially around the nearby Frisco ISD school, was the concern the developer said he heard most; developer claimed the plan generates 'roughly three times less traffic' than current zoning allows. Appearance feedback led to architectural revisions.
- Public comment strongly supportive: P&Z secretary said over 95% of comment cards were in favor; residents spoke in favor at P&Z and council.
- Council tabled the item in August 2026 because officials wanted more discussion; developer called it 'a very challenging zoning process.'
“Sometimes the journey is not always easy, but the destination is something to be celebrated”Angelia Pelham, Frisco Deputy Mayor Pro Tem
Sources: communityimpact.com, communityimpact.com 2, communityimpact.com 3, communityimpact.com 4
H-E-B plans a budget-format Joe V's Smart Shop at 1040 W. Centerville Rd., a former Kroger site vacant since 2006 near LBJ Freeway. A $1.5M grant and 10 years of tax rebates were on Garland's May 19, 2026 council agenda. As of mid-2026 the site was fenced off; no opening date is set.
Site at 1040 W. Centerville Rd. (former Kroger, closed 2006, vacant ~20 years) was fenced off with no other visible progress as of about late July 2026. No opening date.
- Incentive terms: 50% rebate for 10 years on real estate and sales tax; $1.5M cash grant for facade improvements, infrastructure upgrades and demolition; H-E-B to invest at least $7M in the existing center
- Feb. 24, 2026H-E-B announces it will revitalize the ~7-acre vacant center at NE corner of Centerville Rd. and LBJ as North Texas' fourth Joe V's; construction expected 'in the coming months'
- May 19, 2026Development agreement ($1.5M grant, 50%/10-yr tax rebates) on City Council agenda; outcome not confirmed in sources read
- July 2026Site fenced off; no other visible progress (date inferred)
“The approximately seven-acre site will soon be home to North Texas' fourth Joe V's Smart Shop.”H-E-B news release
Sources: dylanhedrick.substack.com, newsroom.heb.com, dallasobserver.com
Regency Centers proposes Flower Mound Center, a 28.58-acre center anchored by a 110,000-130,000-sq-ft H-E-B, south of Waketon Rd. and west of FM 2499. Planners reviewed it in an Aug. 2026 work session; no hearing or vote is set, and H-E-B has not announced the store.
Pre-application/work-session stage. Proposal to return to P&Z; no hearing or council date set. H-E-B has not announced the store and only sent a representative to answer questions.
- 110,000-130,000-sq-ft H-E-B; four ~10,000-sq-ft multi-tenant pad buildings (restaurants with patios; daycare discussed for building with Rippy Rd. access); truck deliveries via a single Waketon Rd. entrance in evenings; parking above town standards requested; retention pond in SW portion; hike-and-bike trail; ~450 trees incl. post oaks; retention walls; LEED-Silver goal
- Aug. 2026Regency Centers presents Flower Mound Center at P&Z work session
- Commissioners and residents raised noise, compatibility, traffic (nearby Marcus High School and a possible Costco about a mile away), drainage/runoff, landscaping, store size and the above-standard parking request, and retention walls creating a 'concrete tunnel' effect; commissioners asked that circus, fair, sewage treatment and mortuary uses be prohibited. Commissioner Michelle Jackson asked whether H-E-B would consider a smaller store.
“This is something we hope brings the town together”Abe Pacetti, Regency Centers
Sources: crosstimbersgazette.com
H-E-B’s North Texas push
H-E-B opened its first Dallas County store in Las Colinas in June 2026 and a Collin County store in Murphy in July. 8 more are in the works, from Denton and Royse City to Carrollton, Garland and the first store inside Dallas city limits at Hillcrest Road and LBJ Freeway. The soonest is the Denton store at I-35W and Robson Ranch Road, which H-E-B now expects to open before 2027; hiring started in August.
Two are worth watching: a budget-format Joe V’s Smart Shop in Garland, a first for North Texas, and a developer-proposed H-E-B in east Flower Mound. H-E-B hasn’t announced the Flower Mound store, and the town hasn’t voted on it. There’s also no H-E-B store announced for Frisco, Plano or McKinney yet. Frisco is getting an H-E-B e-commerce fulfillment center at FM 423 and US 380 for pickup and delivery orders, not a store.
Kroger Marketplace stores
Kroger is building its largest format, the 100,000-to-123,000-sq-ft Marketplace with a pharmacy and fuel center, along the fastest-growing edges of the metro: Sendera Ranch, Anna, McKinney (Custer and Frontier), Fate and Princeton. The Little Elm Marketplace on US 380 opened July 31, 2026.
Costco, BJ’s, Trader Joe’s, Whole Foods, Sprouts and Tom Thumb
- Costco: Celina opened Aug. 26, 2026. Wylie approved a roughly 165,000-sq-ft warehouse on FM 544 in September; state filings show construction through Aug. 2027, but Costco hasn’t announced a date.
- BJ’s Wholesale Club: the warehouse club’s first North Texas store opened in Grand Prairie in May 2026; its Mesquite club opened Nov. 6, 2026 at 4355 Childress Ave. off I-30.
- Trader Joe’s: Frisco‘s first store, at Main St. and Majestic Gardens Dr., won zoning approval Oct. 6, 2026, with no opening date. State filings also show stores planned at Preston Rd. and Spring Creek Pkwy. in Plano and on FM 544 in Wylie, both due by June 2027, though Trader Joe’s says no timeline is set. McKinney‘s second store opened in May.
- Whole Foods: Frisco‘s first Whole Foods is being built out at The Mix on the Dallas North Tollway at Lebanon Rd.; a state filing runs the work through Feb. 2027.
- Sprouts: a new store at Preston Rd. and Frontier Pkwy. in Celina, targeted for 2027, and a state filing for another at US 75 and Rosamond in Anna.
- Tom Thumb: Lucas‘s first standalone supermarket, on Parker Rd., is due late 2026. Argyle‘s Harvest Town Center store opened in March.
Opened in the past year
BJ's fifth Texas club opened Nov. 6, 2026 at 4355 Childress Ave., off I-30 near I-635: a 104,763-sq-ft warehouse club with up to 150 jobs and a 16-position BJ's Gas across Galloway Ave.
Costco opened Aug 26, 2026 at 3445 S. Preston Rd. near Ownsby Pkwy., with a member gas station; about 158,000 sq. ft. per state filings.
Kroger opened its 123,000-square-foot Little Elm Marketplace on July 31, 2026, at the northwest corner of US 380 and FM 2931. It is the first Kroger with the company's Indian Experience product section, and it adds a pharmacy and a 14-position fuel center to a corner that now also has a Target and a Sprouts.
A roughly 122,000-sq-ft H-E-B opened July 22, 2026 at FM 544 and McCreary Road in Murphy, with pharmacy, barbecue drive-thru, sushi bar, fuel station and car wash.
H-E-B opened its first Dallas County store at 2351 W. I-635 in Las Colinas, on the former Fry's Electronics site near Olympus Boulevard.
McKinney's second Trader Joe's opened May 7, 2026 at 8101 Eldorado Parkway, at Stonebridge Drive.
BJ's opened a warehouse club at 1021 IKEA Way in Grand Prairie in May 2026 as part of its Texas launch.
Celina's first Walmart Supercenter opened April 29, 2026 at 1771 N. Preston Rd. in the Shawnee Trail development, at Preston Road and the Collin County Outer Loop.
Tom Thumb opened a grocery store in Harvest Town Center in Argyle on March 6, 2026.
H-E-B's budget-format Joe V's Smart Shop opened its first Irving store, at 2407 W. Airport Fwy., in November 2025.
A Walmart Supercenter opened Nov. 5, 2025 at 1950 McKinney St. in Melissa.
What a new grocery store means if you’re buying
A big grocery store is often the first sign that a growing area has enough rooftops to support shops, restaurants and services. It also brings traffic, delivery trucks and late-night lights. If you’re looking at homes near one of these sites, check the site plan for driveways and screening walls, drive the route at rush hour, and remember that approved projects can still change or stall.
To weigh the bigger picture, compare cities on schools, safety, commute and taxes with Realust Compare, see everything coming to North Texas, or check how home values have changed in each city.
Graphics you can share
Frequently asked questions
When does the Kroger in Sendera Ranch open?
A Kroger representative told Fort Worth's Board of Adjustment in July 2026 that the Marketplace store at Sendera Ranch and Rancho Canyon Way should open before Thanksgiving 2026. Kroger hasn't announced a firm date.
When will H-E-B open in Denton?
H-E-B began hiring for its store at I-35W and Robson Ranch Road in August 2026 and said in September that it expects to open before 2027. A second Denton store, on West University Drive (US 380), is planned for fall to late 2027.
Is H-E-B coming to Dallas?
Yes. Dallas approved zoning in Dec. 2025 for a 131,000-sq-ft H-E-B at Hillcrest Road and LBJ Freeway. A state filing targets a March 2027 start and Sept. 2028 completion. H-E-B has also opened in Irving (Las Colinas) and Murphy.
Is H-E-B coming to Frisco, Plano or McKinney?
No store has been announced in those cities. Frisco is getting an H-E-B e-commerce fulfillment center for pickup and delivery. The closest planned store for Plano is at Josey Lane and Parker Road on the Carrollton side.
Is H-E-B coming to Flower Mound?
A developer, Regency Centers, has proposed a center anchored by an H-E-B south of Waketon Road and west of FM 2499. Planners reviewed it in Aug. 2026, but no vote is set and H-E-B hasn't announced the store.
Is Trader Joe's coming to Frisco?
Yes. After tabling it in August over traffic concerns, Frisco City Council approved zoning on Oct. 6, 2026 for a 12,500-sq-ft Trader Joe's at Main Street and Majestic Gardens Drive. No construction start or opening date has been announced.
When does BJ's open in Mesquite?
BJ's Wholesale Club opens its Mesquite club at 4355 Childress Ave., off I-30 near I-635, on Nov. 6, 2026, with a BJ's Gas station across Galloway Avenue.
Is Trader Joe's coming to Plano or Wylie?
Trader Joe's has filed state construction plans for stores at 5900 Preston Road in Plano and on FM 544 in Wylie, both listed for completion by June 2027. The company confirmed the plans but says no timeline is set.
When will Costco open in Wylie?
Wylie approved zoning in Sept. 2026 for a Costco at 2002 W. FM 544. State filings schedule construction from Oct. 2026 to Aug. 2027. Costco hasn't announced an opening date.
When does the Tom Thumb in Lucas open?
Tom Thumb says the Parker Road store opens later in 2026, and state filings target Dec. 1 for completion. No opening day has been announced.
Sources
- CultureMap Dallas: Kroger Marketplace, Sendera Ranch
- Grocery Dive: Tom Thumb, Lucas
- Community Impact: H-E-B, Robson Ranch Rd.
- Connect CRE: Kroger Marketplace, Anna (Rosamond Crossing)
- Chron (citing the City of Anna): Kroger Marketplace, Anna opening date
- TDLR filing TABS2026017761: Whole Foods, Frisco (The Mix)
- CultureMap Dallas: Kroger Marketplace, Custer & Frontier
- CultureMap Dallas: Kroger Marketplace, Fate
- CultureMap Dallas (Sept. 15, 2026): Trader Joe's, Preston & Spring Creek
- Community Impact: Sprouts, Preston & Frontier
- North Texas e-News (City of Anna announcement): Sprouts, Anna (US 75 & Rosamond)
- Murphy Monitor: Costco, FM 544
- Community Impact: H-E-B, Josey & Parker
- City of Princeton: Kroger Marketplace, Princeton
- Royse City Herald-Banner: H-E-B, Royse City
- CultureMap Dallas: H-E-B, Firewheel Pkwy. & PGBT
- Dallas Observer: H-E-B, Hillcrest & LBJ
- Community Impact: Trader Joe's, Frisco (Main St.)
- Cross Timbers Gazette: H-E-B, FM 2499 & Waketon (proposed)
- BJ's Wholesale Club: BJ's Wholesale Club, Mesquite
- Celina EDC: Costco, Celina
- The Shelby Report: Kroger Marketplace, US 380
- Murphy Monitor: H-E-B, FM 544 & McCreary
- CultureMap Dallas: H-E-B, Las Colinas
- Community Impact: Trader Joe's, Eldorado & Stonebridge
- City of Grand Prairie: BJ's Wholesale Club, Grand Prairie
- CultureMap Dallas: Walmart Supercenter, Celina
- Cross Timbers Gazette: Tom Thumb, Harvest Town Center
- H-E-B Newsroom: Joe V's Smart Shop, Irving
- CultureMap Dallas: Walmart Supercenter, Melissa
Statuses and dates checked Nov. 3, 2026 against city agendas and news releases, Texas Department of Licensing and Regulation (TDLR) construction filings and company announcements. Opening dates are estimates until a company announces them.

